Photo report of the construction of residential complex on the Olesya Gonchara street from 12.02.2021

Residential Complex Construction Report on the Olesya Gonchara street from 12.02.2021.
Photo report of the construction of residential complex on the Olesya Gonchara street from 12.02.2021

As of 02/12/21, despite the difficult weather conditions, the general construction contractor, ChSMP Stroitel-P, is in full swing performing zero cycle works: foundations, walls, columns and ceilings below the +0,000 mark.

The work on the pile field has been completed. Excavation work has been completed to the extent that the technology of construction production allows.

A tower crane was installed and surveyed, a temporary power supply line for machines and mechanisms with a capacity of 300 kW was laid.

Photo report of the construction of residential complex on the Olesya Gonchara street

Photo report of the construction of residential complex on the Olesya Gonchara street